GPA/32
Page 5
The Commission has powers to ensure the full compliance with the directives includes the
power to bring a member State before the Court of Justice. The same power exists when infringement
of the obligations of the GPA is committed by any of the contracting entities covered under the GPA
in any of the member States. An infringement of the obligations under the Directives would relate to
the relationship between Community suppliers and entities and not to the relationship between the
suppliers from the GPA countries and Community entities. As regards the Remedies Directive, if and
when bid challenge rights are not granted in EU legislation because the Remedies Directive may not
have been entirely implemented by a member State, there is a safety net in the community referred to
as the "Francovitch Case Law" which provides suppliers from the GPA Parties other than those from
the EC member States, with the possibility of taking a matter up in the European Court of Justice and
having rapid and effective remedies available as required by the GPA would be able to use the safety
net provided by the Frankovitch Case Law. The "Francovitch" case the Court accepted the principle
that a member State must make good damage suffered by individuals as a result of an infringement of
Community law, e.g. through its failure to transpose a directive into national law or to transpose it
properly. This has been further developed in the "Brasserie du Pêcheur" case. Thus, this safety net
allows any supplier from any GPA country with the possibility to go to court and to have rapid and
effective remedies available to it, as required in the GPA Agreement, therefore, a non-implementation
of the Remedies Directive by a member State does not effect the right of GPA suppliers as they will
be able to use the safety net provided by the "Francovitch Case Law".
Question from the United States
6. Section IV.3 of GPA/20 states that member States are authorized to choose between two
"options" relating to the power of review bodies. Please describe what rapid interim measures, as
required by GPA Article XX:7(a), are provided for in the second option, "indirect pressure".
As stated in Section IV.3 of GPA/20 such "two options" possibility only concerns the legal
regime applicable to Annex 3 entities (contracting entities subject to Directive 93/38). At the time
when Directive 92/13 (the so-called Remedies Utilities Directive) was enacted, it was felt necessary to
take account of the specific nature of certain legal orders in the EC by authorizing the member States
to choose between the introduction of different powers for the review bodies which have equivalent
effects. It is to be noted that claims for damages are always possible.
One of the options includes the power to intervene directly in the contracting entities'
procurement procedures such as by suspending them or by setting aside decisions or discriminatory
clauses in documents or publications. Thus, this option is based on traditional litigation.
However, in some legal orders, review bodies cannot, because of the legal nature of the some
contracting entities, annul or suspend award decisions made by this kind of entities. This is why there
is a second option, referred to in this question, which provide for the power to exert effective indirect
pressure on the contracting entities in order to make them correct any infringements or prevent them
from committing infringements, and to prevent injury from occurring. The kind of measures adopted
are generally making orders for the payment of a particular sum, unless the infringement is corrected
or prevented. This sum must be set at a level high enough to dissuade the contracting entity from
committing or persisting in an infringements. These measures are to be taken at the earliest
opportunity, if possible by way of interlocutory procedures and if necessary by a final procedure on
the substance.
The distinction between the two options concerns the powers exerted by the review bodies
rather than the actual procedure used. In both cases, there is a provision ensuring that measures are
taken at the earliest opportunity.