INGEROP Conseil & Ingénierie
INRA : CREATION D’UN POSTE HT/TGBT n°3 AVEC
SECOURS PAR GROUPE ELECTROGENE
SOMMAIRE
1 PRESCRIPTIONS GENERALES ............................................................................................... 3
1.1 PRESENTATION DU PROJET .......................................................................................... 3
1.2 QUALIFICATION DE L’ENTREPRISE ............................................................................... 6
1.3 PRESTATIONS DUES PAR L’ENTREPRISE .................................................................... 6
1.4 LIAISON AVEC LES AUTRES CORPS D’ETAT ................................................................ 6
1.5 PLAN D’APPEL D’OFFRE .................................................................................................. 7
1.6 PLANNING ......................................................................................................................... 7
1.7 DECLARATION OBLIGATOIRE DES SOUS TRAITANTS ................................................ 8
1.8 MESURES DE PREVENTION ........................................................................................... 8
1.9 RAPPORT BUREAU DE CONTROLE ............................................................................... 8
1.10 PLANS DE CHANTIER ...................................................................................................... 8
1.11 REGLEMENT ................................................................................................................... 11
1.12 CLAUSES ET PRESCRIPTIONS COMMUNES .............................................................. 11
1.13 OBLIGATION DE PRESENTATION DES OFFRES ........................................................ 14
1.14 PRESCRIPTIONS TECHNIQUES GENERALES ............................................................. 16
1.15 PROTECTION, NETTOYAGE .......................................................................................... 20
1.16 PRESCRIPTIONS DIVERSES ......................................................................................... 21
1.17 MISE EN SERVICE .......................................................................................................... 23
1.18 GARANTIE ET ENTRETIEN ............................................................................................ 26
1.19 FORMATION DU PERSONNEL ....................................................................................... 27
2 PRESCRIPTIONS TECHNIQUES GENERALES .................................................................... 28
2.1 STANDARDS ET NORMES ............................................................................................. 28
2.2 PRESCRIPTIONS TECHNIQUES PARTICULIERES ...................................................... 28
3 PRESCRIPTIONS COURANTS FORTS .................................................................................. 31
3.1 HAUTE TENSION ............................................................................................................ 31
3.2 BATTERIE DE CONDENSATEUR ................................................................................... 33
3.3 TABLEAU ELECTRIQUE ................................................................................................. 35
3.4 VENTILLATION DES POSTES 2 ET 3 ............................................................................ 40
3.5 CUVE FIOUL GE 2 ET GE 3 ............................................................................................ 40
3.6 CUVE FIOUL GE 2 ........................................................................................................... 43
3.7 GROUPE ELECTROGENE 1000KVA .............................................................................. 44
4 TRAVAUX DE GROS-ŒUVRE ET D’AMENAGEMENT DES LOCAUX ................................. 54
4.1 TRAVAUX DE GROS-ŒUVRE ET DEMOLITION ........................................................... 54
4.2 TRAVAUX DE SERRURERIE .......................................................................................... 55
4.3 ECLAIRAGE-PC-FM ........................................................................................................ 55
4.4 CHEMINEMENTS ............................................................................................................ 56