00 - MS - CCTV System Installation

Telechargé par Achref Rebhi
METHOD STATEMENT
FOR
CCTV SYSTEM INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
3. HEALTH AND SAFETY
4. OPERATION
5. INSTALLATION AND FIXATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
10. WASTE MANAGEMENT
11. SPECIAL CONTROL MEASURES
12. SUPPORTING DOCUMENTATION
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations of
CCTV system for the project.
This document details the CCTV system Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
PSP : Project Safety Plan
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control Engineer.
WIR : Inspection and Test Request
MIR : Material Verification Record.
3. HEALTH AND SAFETY
Strictly followed as per the manufacturer's Health and Safety
recommendations for handling and use of the materials.
Ensure all involved personnel shall be aware of the same.
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Material used will be as approved by the Engineer.
The sizes and routes routing will be as per the approved Shop
Drawings.
Storage and Protection:
Deliver components parts to site, completely identified in accordance
with shop and certified CAD Drawings prepared for this work.
Store in accordance with the manufacturer’s instructions, above
ground, properly protected from the weather and construction activities.
5. INSTALLATION AND FIXATION
Pre-Installation:
Make sure that civil clearance done prior to start the installation.
Installation will be carried out as per manufacturer
recommendations, Approved shop drawings and project
specifications.
Installation:
Civil Clearance before start the installation of the CCTV system
(Cameras & Panels).
Check that all conduits for the Data of the camera installed as per
approved shop drawings.
Check that all panels installed as per manufacturer
recommendations and all wires Identified.
Check that the CCTV system and its Accessories approved as
per material submittal.
Check that the location of the camera/ panels and the position
set as per approved shop drawings and manufacturer
recommendations.
Check that the Installed Camera is the correct type other (PTZ or
Dome type).
Al specific CCTV camera locations shall be selected to provide a
view of the maximum amount of space.
Refer to relevant CCTV drawing layouts and schematic diagrams
for all active and passive components provided in this section for
exact location and details of integration with other sub-systems.
Check that Integration between the camera and the Access
control system done as per approved schematic diagram and
manufacturer recommendations.
Check that the cameras setting and programmed as per project
requirements and manufacturer recommendations.
Installation of Wires:
Install cables in raceways and cable trays except within consoles,
back boxes, desks, and counters. Conceal raceway and cables
except in unfinished spaces.
Using CAT-6A type cable the maximum length of the cable not
exceeds more than 90 mtrs. Of manufacturer recommendation,
which will provided from structural cabling system supplier.
Comply with requirements for raceways and boxes specified in
Division 26 Section "Raceways, Boxes, Cable Tray, Cable
Ladder and Trunking".
Conceal conductors and cables in accessible ceilings, walls, and
floors where possible.
Wiring within Enclosures:
Bundle, lace, and train cables within enclosures.
Connect to terminal points with no excess and without exceeding
manufacturer's limitations on bending radius.
Grounding
Comply with requirements in Division 26 Section "Grounding and
Bonding for Electrical Systems." for grounding conductors and
connectors.
Comply with ADDC Electricity Wiring Regulations, Sections.
Bond metallic equipment to the system grounding bus bar, using
not smaller than the specified equipment grounding conductor by
ADDC Electricity Wiring Regulations, Sections.
Identification
Identify system components, wiring, and cabling complying with
ADDC Electricity Wiring Regulations. Comply with requirements
for identification specified in Division 26 Section "Identification for
Electrical Systems."
Programming
After making sure all the system installed in correct way
from Subcontractor and supplier, programming of the
system must take place before final testing and
commissioning accourding to Consultant requirement and
senario of the system.
Testing and commissioning of the system submitted
separetly for this system mentioned all the procedure of
Testing of the system and commissioning it.
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the
system after the installation is completed.
This instruction shall be scheduled at the convenience of the
staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shop drawings, approved specs and manufacturer
recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
2. To ensure that the progressing of works is carried out according
to the planned program and as per the approved method of
statement.
3. To ensure that all the equipment and material required
executing the work are available according to the planned
construction program.
4. To co-ordinate with the Main contractor, MEP coordinator,
Safety Officer for a safe and proper execution of the works.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
2. To provide all necessary information and distribute
responsibilities to his construction.
1 / 9 100%
La catégorie de ce document est-elle correcte?
Merci pour votre participation!

Faire une suggestion

Avez-vous trouvé des erreurs dans linterface ou les textes ? Ou savez-vous comment améliorer linterface utilisateur de StudyLib ? Nhésitez pas à envoyer vos suggestions. Cest très important pour nous !