Specify the procedure for workplace acceptance after repair.
After the work is fully completed, the work performer or supervisor must
remove the team from the workplace, remove temporary fences, portable safety
posters, flags and grounding devices installed by the team, lock the doors of the
electrical installation. After checking the workplaces, the work performer signs the
work-permit. After receiving the work-permit, the admitting person must inspect the
workplaces and inform the dispatcher about the full completion of work and the
possibility of putting the electrical installation into operation.