Inspection and Test Notification (ITN)
Project Name : TIZERT COPPER PROJECT
N° du projet: SP0904
Plant :
ITN No. :
Notification‐SENET‐GC‐55
Date :
14/02/24
CIG
No.
Autre
ITP No./ Item No. Description of inspection
Topo-Inspection
Formwork & Anchor bolts
And Pouring Concrete
30MPA
Inspection for Rebar
1
Location
- OXIDE
FLOTATION
B1-4 & B1-3
For plinths(P1)
and (P2)
- (B5-B4-B3-B2) IN
Tailing thickener
- Oxide flotation
B3-B4 & B5
- Tailing Thickener
- Oxide and
Sulphide
Flotation
- Crushed ore
stockpile tunnel
- Tower cantilever
Inspection for Bottom
- Room
Stockpile
Tunnel
- Tailing
thickener Axe 4
(B5-B4-B3-B2)
Apply the SIKA GROUT
for rock anchors
- TAILINGS
THICKENER B5
- Oxide &
Sulphide Flotation
ITP-SEAM-CIG-00
Excavation
REBAR & Formwork
- TAILINGS
THICKENER
FOUNDATIONS
- TAILINGS
THICKENER
FOUNDATIONS
- Crushed ore
stockpile tunnel
- Tower cantilever
-Oxide & Sulphide
Flotation
Date & Time
12/02/2024
09H00
15/02/2024
09H00
Remark
Cleaning
Leane concrete
Name
Aass Radouane
Prepared by SEAM CQS:
Reviewed by SEAM Const.:
Tarik Ait menzar
- Room Stockpile
Tunnel
- Rom Escape
stockpile tunnel
- Tailing Thickener
- Oxide Flotation
Date
Signature
14/02/2024
14/02/2024
Reviewed by SENET Const.:
Received by Managem QA/QC:
Inspection Result :
Report :
Accepted
Not Accepted
Re-scheduled
Date/Time:
Remarks :