Inspection and Test Notification (ITN) Project Name : TIZERT COPPER PROJECT N° du projet: SP0904 Plant : ITN No. : Notification‐SENET‐GC‐55 Date : 14/02/24 CIG No. Autre ITP No./ Item No. Description of inspection Topo-Inspection Formwork & Anchor bolts And Pouring Concrete 30MPA Inspection for Rebar 1 Location - OXIDE FLOTATION B1-4 & B1-3 For plinths(P1) and (P2) - (B5-B4-B3-B2) IN Tailing thickener - Oxide flotation B3-B4 & B5 - Tailing Thickener - Oxide and Sulphide Flotation - Crushed ore stockpile tunnel - Tower cantilever Inspection for Bottom - Room Stockpile Tunnel - Tailing thickener Axe 4 (B5-B4-B3-B2) Apply the SIKA GROUT for rock anchors - TAILINGS THICKENER B5 - Oxide & Sulphide Flotation ITP-SEAM-CIG-00 Excavation REBAR & Formwork - TAILINGS THICKENER FOUNDATIONS - TAILINGS THICKENER FOUNDATIONS - Crushed ore stockpile tunnel - Tower cantilever -Oxide & Sulphide Flotation Date & Time 12/02/2024 09H00 15/02/2024 09H00 Remark Cleaning Leane concrete Name Aass Radouane Prepared by SEAM CQS: Reviewed by SEAM Const.: Tarik Ait menzar - Room Stockpile Tunnel - Rom Escape stockpile tunnel - Tailing Thickener - Oxide Flotation Date Signature 14/02/2024 14/02/2024 Reviewed by SENET Const.: Received by Managem QA/QC: Inspection Result : Report : Accepted Not Accepted Re-scheduled Date/Time: Remarks :